Active Project List |
Return to Project listing | Print this page |
Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2022-07-01 A |
Kickoff | 2022-09-19 A |
Stage 2 - 30% | 2022-11-07 A |
Stage 3 - 60% | 2023-01-23 A |
Stage 4 - 95% | 2023-03-27 A |
EPG Clearance | 2023-03-27 A |
RW Clearance | 2023-04-24 A |
URR Clearance | 2023-04-10 A |
Stage 5 - 100% | 2023-05-01 A |
Advertise | 2023-06-02 A |
Bids Opening | 2023-10-02 A |
|
Arizona Department of Transportation |