Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
EPG Clearance | 2024-01-09 A |
RW Clearance | 2024-03-21 A |
URR Clearance | 2024-03-30 |
Stage 5 - 100% | 2024-05-02 |
Advertise | 2024-09-16 A |
|