Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2020-12-16 A |
Kickoff | 2021-01-14 A |
Stage 1 - 15% | 2021-06-18 A |
Stage 4 - 95% | 2021-10-01 A |
EPG Clearance | 2021-10-25 A |
RW Clearance | 2021-10-28 A |
URR Clearance | 2021-11-05 A |
Stage 5 - 100% | 2022-02-02 A |
Advertise | 2022-05-26 A |
Bids Opening | 2022-07-29 A |
|