RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
101L MA 12.0 F031601C CL 75TH AVE - I-17 MI1O ADD GENERAL PURPOSE LANES RASHIDUL HAQUE
602-712-7352
3/28/2024 Jeff Ross
602-712-8477
Current Program Budget $198,089,000 Program FY 24

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2020-09-04 A
Kickoff 2020-07-30 A
Stage 2 - 30% 2021-07-15 A
Stage 3 - 60% 2022-01-14 A
Stage 4 - 95% 2023-10-16 A
EPG Clearance 2022-04-25 A
RW Clearance 2023-10-31 A
URR Clearance 2024-02-06 A
Stage 5 - 100% 2024-02-16 A
Advertise 2024-03-28 A
Bids Opening 2024-07-20