RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
347 PN 178.0 F068201C CL CASA BLANCA RD AND CEMENT PLANT A LP1Q INTERSECTION IMROVEMENTS REHNUMA RAHMAN
602-712-7342
8/29/2025 Lee Makler
602-712-8579
Current Program Budget   Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2023-06-02 A
Kickoff 2023-07-11 A
Stage 2 - 30% 2024-10-25
Stage 3 - 60% 2024-12-24
Stage 4 - 95% 2025-05-31
EPG Clearance 2025-05-31
RW Clearance 2025-07-01
URR Clearance 2025-07-01
Stage 5 - 100% 2025-07-01
Advertise 2025-08-30
Bids Opening 2025-10-18