Milestone Name | Date ("A" denotes actual finish) |
Stage 4 - 95% | 2023-08-16 |
EPG Clearance | 2024-03-23 |
RW Clearance | 2023-10-13 |
URR Clearance | 2025-01-11 |
Stage 5 - 100% | 2023-10-04 |
Advertise | 2025-09-23 |
|