Active Project List |
Return to Project listing | Print this page | |||||||||||||||||||||||||||||||||
|
Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2024-05-17 A |
Kickoff | 2024-07-26 A |
Stage 2 - 30% | 2024-09-12 A |
Stage 3 - 60% | 2024-10-24 A |
Stage 4 - 95% | 2025-01-29 |
EPG Clearance | 2025-01-21 |
RW Clearance | 2025-02-05 |
URR Clearance | 2025-02-01 |
Stage 5 - 100% | 2025-04-05 |
Advertise | 2025-05-01 |
Bids Opening | 2025-06-12 |
|
Arizona Department of Transportation |