Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2024-08-19 A |
Kickoff | 2024-08-19 A |
Stage 2 - 30% | 2024-12-02 A |
Stage 3 - 60% | 2025-03-27 |
Stage 4 - 95% | 2025-06-04 |
EPG Clearance | 2025-05-22 |
RW Clearance | 2025-05-31 |
URR Clearance | 2025-07-01 |
Stage 5 - 100% | 2025-07-16 |
Advertise | 2025-08-09 |
Bids Opening | 2025-08-12 |
|