ADOTNet : Home

Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 PM TUC T048401C SC TANQUE VERDE RD; TANQUE VERDE WAS KL1Q STREET LIGHTING DANA CHERRY
602-712-7030
8/15/2025 Lee Makler
602-712-8579
Current Program Budget $661,000 Program FY 26

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
Stage 4 - 95% 2025-04-02
EPG Clearance 2024-10-05
RW Clearance 2025-05-02
URR Clearance 2025-05-02
Stage 5 - 100% 2025-07-02
Advertise 2025-08-16




For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation