Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2024-02-08 A |
Stage 3 - 60% | 2024-11-04 A |
Stage 4 - 95% | 2024-10-31 A |
EPG Clearance | 2024-09-03 A |
RW Clearance | 2024-11-14 A |
URR Clearance | 2024-11-25 A |
Stage 5 - 100% | 2024-12-19 |
Advertise | 2025-03-01 |
Bids Opening | 2025-04-19 |
|