Milestone Name | Date ("A" denotes actual finish) |
NTP | 2024-03-01 A |
Stage 4 - 95% | 2024-04-15 A |
EPG Clearance | 2024-06-17 A |
RW Clearance | 2024-05-30 A |
URR Clearance | 2024-05-02 A |
Stage 5 - 100% | 2024-05-21 A |
Advertise | 2024-06-27 A |