Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
Kickoff | 2024-07-01 A |
Stage 3 - 60% | 2024-10-28 A |
Stage 4 - 95% | 2025-01-13 A |
EPG Clearance | 2024-11-27 A |
RW Clearance | 2024-12-12 A |
URR Clearance | 2025-03-25 A |
Stage 5 - 100% | 2025-04-01 A |
Advertise | 2025-04-16 A |
Bids Opening | 2025-06-11 |
|