| Project Milestones | |
|---|---|
| Milestone Name | Date ("A" denotes actual finish) | 
| NTP | 2020-09-24 A | 
| Kickoff | 2020-10-07 A | 
| Stage 1 - 15% | 2020-12-11 A | 
| Stage 2 - 30% | 2021-01-18 A | 
| Stage 3 - 60% | 2021-04-23 A | 
| Stage 4 - 95% | 2021-07-29 A | 
| EPG Clearance | 2021-07-29 A | 
| RW Clearance | 2021-07-19 A | 
| URR Clearance | 2021-10-06 A | 
| Stage 5 - 100% | 2022-08-23 A | 
| Advertise | 2025-07-29 A | 
| Bids Opening | 2025-10-18 | 
|  | 