Milestone Name | Date ("A" denotes actual finish) |
NTP | 2020-09-24 A |
Kickoff | 2020-10-07 A |
Stage 1 - 15% | 2020-12-11 A |
Stage 2 - 30% | 2021-01-18 A |
Stage 3 - 60% | 2021-04-23 A |
Stage 4 - 95% | 2021-07-29 A |
EPG Clearance | 2021-07-29 A |
RW Clearance | 2021-07-19 A |
URR Clearance | 2021-10-06 A |
Stage 5 - 100% | 2022-08-23 A |
Advertise | 2025-03-15 |
Bids Opening | 2025-06-21 |
|