RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 PM ORV T047401C SC TANGERINE RD & 1ST AVE; TANGERINE JU1Q UPDATE TRAFFIC SIGNALS ARASH GHAZANFARI
602-712-8336
12/4/2024 Lee Makler
602-712-8579
Current Program Budget $309,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2024-01-05 A
Kickoff 2024-01-17 A
Stage 3 - 60% 2024-05-24 A
Stage 4 - 95% 2024-08-12 A
EPG Clearance 2024-08-08 A
RW Clearance 2024-08-22 A
URR Clearance 2024-10-04 A
Stage 5 - 100% 2024-10-24 A
Advertise 2024-12-17
Award Date 2025-02-03




For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation