![]() |
Active Project List |
Return to Project listing | Print this page | |||||||||||||||||||||||||||||||||
|
Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2023-12-05 A |
Kickoff | 2023-12-05 A |
Stage 3 - 60% | 2024-09-21 |
Stage 4 - 95% | 2024-11-21 |
EPG Clearance | 2024-09-28 |
RW Clearance | 2024-10-12 |
URR Clearance | 2024-12-07 |
Stage 5 - 100% | 2025-01-11 |
Advertise | 2025-01-16 |
Bids Opening | 2025-02-22 |
|
Arizona Department of Transportation |