ADOTNet : Home

Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
60 MA 110.0 F068401C NW MORRISTOWN - WICKENBURG IU1Q PAVEMENT REHABILITATION TRICIA BROWN
602-712-7046
6/16/2025 Lee Makler
602-712-8579
Current Program Budget $10,400,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
Kickoff 2024-10-15 A
Stage 1 - 15% 2023-08-25 A
Stage 2 - 30% 2023-10-04 A
Stage 3 - 60% 2025-02-01
Stage 4 - 95% 2025-04-01
EPG Clearance 2025-04-16
RW Clearance 2025-02-15
URR Clearance 2025-05-01
Stage 5 - 100% 2025-05-16
Advertise 2025-06-15
Bids Opening 2025-08-16




For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation