Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2024-07-11 A |
Kickoff | 2024-10-28 A |
Stage 2 - 30% | 2025-03-06 |
Stage 3 - 60% | 2025-09-12 |
Stage 4 - 95% | 2026-01-31 |
EPG Clearance | 2025-12-17 |
RW Clearance | 2026-04-11 |
URR Clearance | 2026-03-17 |
Stage 5 - 100% | 2026-04-21 |
Advertise | 2026-06-12 |
Bids Opening | 2026-08-22 |
|