Active Project List |
Return to Project listing | Print this page | |||||||||||||||||||||||||||||||||
|
Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2024-04-29 A |
Stage 3 - 60% | 2024-10-04 A |
Stage 4 - 95% | 2025-03-06 |
EPG Clearance | 2025-03-01 |
RW Clearance | 2025-03-13 |
URR Clearance | 2025-03-14 |
Stage 5 - 100% | 2025-04-17 |
Advertise | 2025-05-16 |
Bids Opening | 2025-05-17 |
|
Arizona Department of Transportation |