Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
Stage 2 - 30% | 2024-04-20 A |
Stage 3 - 60% | 2024-10-15 A |
Stage 4 - 95% | 2025-03-11 |
EPG Clearance | 2025-03-08 |
Stage 5 - 100% | 2025-04-29 |
Advertise | 2025-07-02 |
|