Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
10 MA 112.5 F066001D CL SR 85 - CITRUS RD GS1Q ADD GENERAL PURPOSE LANE PATRICK O'LESKE
602-712-7629
6/9/2027 Lee Makler
602-712-8579
Current Program Budget $116,198,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2024-03-18 A
Kickoff 2024-06-05 A
Stage 2 - 30% 2024-12-03 A
Stage 3 - 60% 2025-02-14
Stage 4 - 95% 2026-05-28
EPG Clearance 2026-05-28
RW Clearance 2026-06-04
URR Clearance 2026-06-05
Stage 5 - 100% 2026-06-05
Advertise 2027-06-09
Bids Opening 2027-08-20