Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2024-05-01 A |
Kickoff | 2024-05-22 A |
Stage 2 - 30% | 2024-10-29 |
Stage 3 - 60% | 2025-01-11 |
Stage 4 - 95% | 2025-03-08 |
EPG Clearance | 2025-03-08 |
RW Clearance | 2025-03-15 |
URR Clearance | 2025-03-18 |
Stage 5 - 100% | 2025-04-19 |
Advertise | 2025-05-15 |
Bids Opening | 2025-07-10 |
|