Active Project List |
Return to Project listing | Print this page | |||||||||||||||||||||||||||||||||
|
Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2023-11-16 A |
Kickoff | 2023-12-11 A |
Stage 2 - 30% | 2024-07-10 A |
Stage 3 - 60% | 2024-11-12 A |
Stage 4 - 95% | 2025-03-29 |
EPG Clearance | 2025-03-29 |
RW Clearance | 2025-03-29 |
URR Clearance | 2025-04-03 |
Stage 5 - 100% | 2025-04-26 |
Advertise | 2025-06-14 |
Bids Opening | 2025-08-22 |
|
Arizona Department of Transportation |