Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
Stage 2 - 30% | 2023-09-07 A |
Stage 3 - 60% | 2023-12-08 A |
Stage 4 - 95% | 2024-01-26 A |
EPG Clearance | 2024-02-27 A |
RW Clearance | 2024-02-14 A |
URR Clearance | 2024-02-20 A |
Stage 5 - 100% | 2024-03-08 A |
Advertise | 2024-05-16 |
Bids Opening | 2024-07-20 |
|