RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
93 YV 156.0 F063801C NW PLACERITAS CREEK - DATE CREEK GB1Q PAVEMENT REHABILITATION OLIVIER MIRZA
602-712-4032
8/29/2025 Lee Makler
602-712-8579
Current Program Budget $39,934,000 Program FY 26

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2023-08-30 A
Stage 3 - 60% 2024-02-13 A
Stage 4 - 95% 2025-06-07
EPG Clearance 2025-06-30 A
RW Clearance 2025-06-26 A
URR Clearance 2025-06-27 A
Stage 5 - 100% 2025-08-02
Advertise 2025-08-30
Bids Opening 2026-01-17