RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 MA LHV T043501C NW SSFB SIGNS - LHC 10 VARIOUS LOCA FH1Q INSTALL SPEED FEEDBACK SIGNS PEDRAM SHAFIEIAN
602-712-8166
6/28/2024 Lee Makler
602-712-8579
Current Program Budget $743,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2024-06-11
Kickoff 2024-06-20
Stage 2 - 30% 2024-07-05
Stage 3 - 60% 2024-08-16
Stage 4 - 95% 2024-10-11
EPG Clearance 2024-10-11
RW Clearance 2024-10-18
URR Clearance 2024-10-19
Stage 5 - 100% 2024-11-01
Advertise 2024-11-23
Bids Opening 2024-11-26