ADOTNet : Home

Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 MA LHV T043501C NW SSFB SIGNS - LHC 10 VARIOUS LOCA FH1Q INSTALL SPEED FEEDBACK SIGNS PEDRAM SHAFIEIAN
602-712-8166
2/14/2025 Lee Makler
602-712-8579
Current Program Budget $743,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2024-06-11
Kickoff 2024-09-11
Stage 2 - 30% 2024-09-26
Stage 3 - 60% 2024-11-07
Stage 4 - 95% 2025-01-02
EPG Clearance 2025-01-02
RW Clearance 2025-01-09
URR Clearance 2025-01-10
Stage 5 - 100% 2025-01-23
Advertise 2025-02-14
Bids Opening 2025-02-15