RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 PM ORV T043801C SC NARANJA DR, LA CANADA DR - FIRST FC1Q CONSTRUCT MULTI-USE PATH ARASH GHAZANFARI
602-712-8336
9/13/2024 Lee Makler
602-712-8579
Current Program Budget $2,891,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2023-09-22 A
Kickoff 2023-10-05 A
Stage 2 - 30% 2024-06-01
Stage 3 - 60% 2024-05-04
Stage 4 - 95% 2024-07-13
EPG Clearance 2024-06-22
RW Clearance 2024-06-29
URR Clearance 2024-08-03
Stage 5 - 100% 2024-08-31
Advertise 2024-09-14
Bids Opening 2024-09-17