![]() |
Active Project List |
| Return to Project listing | Print this page |
| Project Milestones | |
|---|---|
| Milestone Name | Date ("A" denotes actual finish) |
| NTP | 2023-09-22 A |
| Kickoff | 2023-10-05 A |
| Stage 2 - 30% | 2024-07-15 A |
| Stage 3 - 60% | 2024-05-09 A |
| Stage 4 - 95% | 2024-10-07 A |
| EPG Clearance | 2024-07-30 A |
| RW Clearance | 2024-08-07 A |
| URR Clearance | 2025-03-10 A |
| Stage 5 - 100% | 2025-03-10 A |
| Advertise | 2025-04-03 A |
| Bids Opening | 2025-07-18 A |
| |
| Arizona Department of Transportation |