RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
10 PM 254.0 F062501C SC PRINCE RD - I-19 TI FB1Q CONVERT HPS TO LED LIGHTING JEFFREY DAVIDSON
602-712-8534
5/17/2024 Lee Makler
602-712-8579
Current Program Budget $2,600,000 Program FY 24

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2023-09-11 A
Kickoff 2023-09-29 A
Stage 3 - 60% 2023-10-25 A
EPG Clearance 2023-12-19 A
RW Clearance 2024-01-20 A
URR Clearance 2024-01-08 A
Stage 5 - 100% 2024-05-02
Advertise 2024-05-17
Bids Opening 2024-07-20