RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
202L MA 1.0 F062101C CL 24TH ST - SCOTTSDALE RD ES1Q CONVERT HPS TO LED LIGHTING JEFFREY DAVIDSON
602-712-8534
4/9/2024 Lee Makler
602-712-8579
Current Program Budget $1,400,000 Program FY 24

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2023-08-17 A
Kickoff 2023-06-30 A
Stage 3 - 60% 2023-10-25 A
Stage 4 - 95% 2024-01-26 A
EPG Clearance 2024-01-09 A
RW Clearance 2024-01-03 A
URR Clearance 2024-02-09 A
Stage 5 - 100% 2024-03-25 A
Advertise 2024-04-09 A
Bids Opening 2024-09-03
Award Date 2024-10-03