ADOTNet : Home

Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 MA PHX T042401C CL 32ND STREET & THOMAS RD EF1Q INTERSECTION SAFETY IMPROVEMENTS DANA CHERRY
602-712-7030
8/16/2024 Lee Makler
602-712-8579
Current Program Budget $1,200,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
Stage 4 - 95% 2024-09-16 A
EPG Clearance 2025-02-04
RW Clearance 2025-02-13
URR Clearance 2025-05-16
Stage 5 - 100% 2025-01-24 A
Advertise 2025-09-02




For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation