Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
89 CN 551.2 F060901X NC PAGE PORT OF ENTRY EE1Q REPLACE SCALE CHRIS MOORE
602-712-2132
TBD Lee Makler
602-712-8579
Current Program Budget $1,300,000 Program FY 29

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2023-03-22 A
Kickoff 2023-04-03 A
Stage 3 - 60% 2023-04-21 A
Stage 4 - 95% 2023-06-14 A
EPG Clearance 2023-06-12 A
RW Clearance 2023-05-03 A
URR Clearance 2023-06-13 A
Stage 5 - 100% 2023-06-19 A
Advertise 2023-06-20 A
Bids Opening 2023-09-15
Award Date 2023-09-26