RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 MA GLB T042301C CL STACEY RD; HIGLEY RD - 172ND ST ED1Q IMPROVE UNPAVED ROADWAY PATRICK O'LESKE
602-712-7629
5/23/2025 Lee Makler
602-712-8579
Current Program Budget $3,208,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2023-12-11 A
Kickoff 2024-04-22 A
Stage 2 - 30% 2024-11-02
Stage 3 - 60% 2025-01-11
Stage 4 - 95% 2025-03-08
EPG Clearance 2025-03-08
RW Clearance 2024-09-28
URR Clearance 2025-03-13
Stage 5 - 100% 2025-05-01
Advertise 2025-05-23
Bids Opening 2024-12-21