Active Project List |
Return to Project listing | Print this page |
Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2021-06-25 A |
Kickoff | 2021-08-09 A |
Stage 2 - 30% | 2021-09-24 A |
Stage 3 - 60% | 2021-12-03 A |
Stage 4 - 95% | 2022-01-31 A |
EPG Clearance | 2021-12-28 A |
RW Clearance | 2022-01-03 A |
URR Clearance | 2022-01-03 A |
Stage 5 - 100% | 2022-04-08 A |
Advertise | 2022-10-06 A |
Bids Opening | 2023-04-24 A |
|
Arizona Department of Transportation |