ADOTNet : Home

Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 PM PIM T040501C SC AJO WASH BRIDGE CO1Q REPLACE BRIDGE DANA CHERRY
602-712-7030
TBD Lee Makler
602-712-8579
Current Program Budget $761,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
Stage 4 - 95% 2025-03-29
EPG Clearance 2025-02-11
RW Clearance 2025-02-11
URR Clearance 2025-02-11
Stage 5 - 100% 2025-04-16




For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation