Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2019-08-30 A
Stage 1 - 15% 2019-08-30 A
Stage 3 - 60% 2019-08-30 A
Stage 4 - 95% 2021-04-26 A
EPG Clearance 2021-05-11 A
RW Clearance 2021-11-09 A
URR Clearance 2022-02-25 A
Stage 5 - 100% 2022-08-29 A
Advertise 2022-09-23 A
Bids Opening 2022-12-27 A
Award Date 2023-01-23 A