Milestone Name | Date ("A" denotes actual finish) |
Stage 4 - 95% | 2023-11-13 A |
EPG Clearance | 2024-08-29 A |
RW Clearance | 2024-10-19 |
URR Clearance | 2024-03-23 |
Stage 5 - 100% | 2024-01-02 A |
Advertise | 2025-05-01 |
|